March 21 (Reuters) - AMERICAN ELECTRIC POWER COMPANY
INC'S ( AEP ) INDIANA MICHIGAN POWER:
* REPORTS COOK NUCLEAR PLANT UNIT 2 WILL BEGIN ITS
TWENTY-SEVENTH REFUELING OUTAGE ON MARCH 23
* REPORTS POWER ON UNIT 2 WAS REDUCED ON MARCH 20 TO ALLOW
FOR EQUIPMENT TESTING BEFORE THE OUTAGE BEGINS
* REPORTS THE UNIT 2 WILL HAVE OPERATED FOR 12,023 HOURS
DURING ITS LAST CYCLE AT A CAPACITY FACTOR OF 99.4%, GENERATING
14,094,064 MEGAWATT-HOURS OF (NET) ELECTRICITY
* REPORTS COOK UNIT 1 REMAINS AT 100% AND POWER TO CUSTOMERS
IS NOT EXPECTED TO BE DISRUPTED BY THE PLANNED UNIT 2 OUTAGE
* REPORTS AEP DOES NOT PROVIDE A RETURN TO SERVICE DATE FOR
COMPETITIVE REASONS
(Reporting by Sherin Elizabeth varghese in Bengaluru)