* Ameren ( AEE ) projects winter 2032 capacity shortfall of about
1,500 MW after plant startup
* Shortfall grows to about 2,300 MW in 2033, Ameren ( AEE )
estimates
* Regulatory process starts with August 20 prehearing
conference before Missouri Public Service Commission
By Tim McLaughlin
July 30 (Reuters) - Ameren's ( AEE ) planned mega gas plant for the
Midwest will still leave the utility short of the power and
reserves needed to meet surging data center demand, the
company's own analysis showed ahead of a key approval process
next month.
The projected shortfall highlights mounting strain on U.S.
power grids as data center demand grows faster than the
generation and transmission capacity needed to support it.
St. Louis-based Ameren's ( AEE ) urgency for the project is acute
after signing contracts this year to provide electricity to data
centers in development by Amazon ( AMZN ) and Alphabet's Google
in rural Missouri.
Ameren ( AEE ) says the 2,100-megawatt West Alton Energy
Center is necessary, but would not fully restore the reserve
cushion needed to meet projected demand. The project is planned
for a site next to a coal plant on the banks of the Mississippi
River about 28 miles (45 km) northwest of St. Louis.
"The company's resource capacity still falls well short of
the total demand" and planned reserve margin, Ameren Director of
Corporate Analysis Matt Michels said in July 24 testimony filed
with the Missouri Public Service Commission.
An August 20 prehearing conference will kick off the
regulatory process for Ameren ( AEE ) to obtain approval to construct
the power plant.
Ameren ( AEE ) estimates the plant would come online in late 2031.
But Ameren's ( AEE ) capacity shortfall in the winter of 2032, for
example, would equal about 1,500 MW and grow to about 2,300 MW
the following year, Michels said in his testimony.
Ameren ( AEE ) executives say the utility also will build capacity
by enhancing existing power sources, developing solar and
battery energy storage sites and purchasing power from the
regional grid.
Ameren's ( AEE ) service area falls within the Midcontinent ISO,
which manages the flow of electricity for a territory that
includes all or part of 15 U.S. states in the Midwest and South.
The total return on Ameren's ( AEE ) stock over the past 12 months
is 12.7%, outpacing the 8.4% for the S&P 500 Utilities Sector
, as investors anticipate strong earnings growth over
the next decade.
"Ameren ( AEE ) anticipates more than $70 billion of additional
investment opportunities over the next 10 years, providing a
long runway of growth," Morningstar analyst Andrew Bischof wrote
this week in a research note.
"The most attractive opportunities are supporting data
center development in Illinois and Missouri, new generation in
Missouri, modernizing the grid in Illinois and Missouri, and
transmission expansion across the Midcontinent electric grid,"
Bischof said.