* Government tries to prevent power deficit from growing
* New rationing measures began in capital Caracas
* 10-hour per day cuts have become normal in many regions
* Businesses, factories forecast reduced sales, output amid
poor public services
By Tibisay Romero, Mariela Nava and Marianna Parraga
VALENCIA/MARACAIBO/LA GUAIRA, Aug 13 (Reuters) - Less than
two months after devastating twin earthquakes left more than
6,000 dead, Venezuelans are being called by the government to
save power and water.
With a drought looming, many read this as an omen of more
widespread electricity outages and less fresh water supply after
months of already severe cuts.
Interim President Delcy Rodriguez said last week that El
Niño was already hitting the OPEC country and could bring
drought before year-end. The periodic phenomenon, which warms
the Pacific Ocean's surface altering global weather patterns,
made power and water conservation necessary, she said.
The call for expanded conservation on the already challenged
grid has triggered fresh protests across regions where people
and businesses face electricity cuts of up to 10 hours per day,
frequent equipment malfunctions that lead to days-long power
outages and intermittent water supply.
"I can't wrap my head around more power savings measures if
we don't have it at all," said Mariela Nunez, a 75-year-old
retired teacher in the central city of Valencia, where daily
power cuts are getting longer.
"They cut it without notice," she added. "The heat does not
allow us to sleep and we have no elevator to go up and down to a
12th-floor apartment."
Venezuela has less than 13,000 megawatts (MW) of generation
capacity available out of 36,000 MW installed, leaving a
shortfall of more than 1,500 MW between current supply and
demand that authorities are trying to keep from widening.
Nearly 90% of thermal capacity is out of service after years
of underinvestment and delayed maintenance, energy expert Nelson
Hernandez said in a report earlier this year. That has increased
dependence on hydropower, mostly from the Guri dam system in the
south, to more than 80%.
Rodriguez has promised that up to 4,800 MW of installed
capacity will be restored before year-end, saying recently
signed contracts with GE Vernova ( GEV ) and IMPSA for upgrades
and new turbines would also boost supply.
Past promises that went unmet, however, have left many
skeptical.
"We must be honest. El Niño is not the cause of the public
services' crisis," said Jose Antonio Robles, who leads Zulia
state's engineers' center. "It is only aggravating a
long-standing deficit."
He blamed the current need for rationing on years of
underinvestment in generation and deterioration of transmission
and distribution lines, which have made the system unable to
meet increased demand.
Drought and wildfires could also threaten agricultural
output, adding to the hardship from power and water rationing,
said Abraham Salcedo, who directs the school of civil
engineering at Venezuela's Central University.
Venezuela's information ministry and utility Corpoelec did
not reply to requests for comment.
POWER CUTS CLOUD QUAKE RECOVERY EFFORTS
In Caracas, the government last week ordered office
buildings and malls to switch elevators off three hours per day,
while some ministries and public offices have reduced service to
three days per week until further notice.
Factories, shops and farms hit by poor services or still
recovering from the quakes expect lower output and revenue
losses if supply tightens further, business chambers said.
Some public hospitals and private clinics are reinforcing
emergency care with generators, according to nurses and doctors.
"How will companies install in Venezuela? How will they grow
if there's no certainty over the national power system's
restoration?" asked Ernesto Abbas, who leads the commerce
chamber of central Carabobo, an industrial state increasingly
affected by electricity cuts.
In the cities worst hit by the twin quakes, including
largely devastated La Guaira on the northern coast, families
have lived in tents outside their damaged buildings for weeks
and say they cannot bear any more bad news.
"I have no idea of what we'll do," said Josefina Rodriguez,
59, a former public worker guarding her daughter's apartment
from a tent outside while waiting for official word on whether
it will be repaired or demolished. With no running water and
only a cable from a neighboring building to power a light bulb
and a fan, she fears the new rationing will make things worse.
In the neighborhood of Tanaguarena in La Guaira, where
dozens of buildings collapsed and rescuers are still taking
bodies out of the rubble, a small river that runs to a beach
where trucks are dumping debris is all homeless families have to
bathe and wash their clothes.