CALGARY, July 31 (Reuters) - Canadian pipeline operator
Enbridge ( ENB ) said on Friday it was postponing the
250,000-barrel-per-day second phase of its Mainline crude
pipeline network, partly due to Canadian oil producers not
committing to significant output increases.
The project would have increased exports of Canadian crude
to U.S. refineries.
But Enbridge ( ENB ) CEO Greg Ebel said the company will focus first
on its 100,000 bpd Flanagan South Expansion and its 50,000 bpd
Southern Access Extension, which will add capacity to two
secondary pipelines that connect to the Mainline in Illinois and
transport crude to multiple U.S. refining centers and the Gulf
Coast.
Ebel said Canada is facing a generational opportunity to
expand its oil output, thanks to recent federal government
policy changes and the rollback of some environmental rules.
But he said while a recent agreement between the federal
government and Alberta aimed at accelerating oil sands growth
could have a dramatic impact, most of the proposed changes
remain non-binding and have not been enshrined into law.
Enbridge ( ENB ) does not expect Canadian oil sands companies to
meaningfully boost production until there is more policy and
regulatory certainty, said Colin Gruending, the company's
president of liquids pipelines.
"Nor do we expect producers to be making binding FID-able
commitments to new pipelines until then," Gruending said,
referring to final investment decisions.
A company spokesperson confirmed the decision to prioritize
the secondary pipeline projects means a delay for the Mainline
phase two project, which Enbridge ( ENB ) had previously said could be
in service by the end of 2028.