NEW YORK, May 20 (Reuters) - Canadian energy firm
Enbridge ( ENB ) launched an open season process earlier this
week for its proposed Project Beacon to upgrade its existing
Algonquin Gas Transmission natural gas pipeline system in New
England.
* The project is designed to bring additional energy into
the Northeast and help address ongoing high energy costs and
reliability concerns, Enbridge ( ENB ) said.
* The open season allows customers - such as gas utilities
and power plants - to indicate how much gas they may need in the
future.
* The project is designed to upgrade existing infrastructure
along existing pipeline corridors, which helps increase energy
access while minimizing construction impacts.
* The Northeast faces higher energy costs than the rest of
the country, particularly during very cold winters and hot
summers when demand peaks.
* If customer commitments are secured and regulatory
approvals are obtained, Project Beacon could be in service by
2030, Enbridge ( ENB ) said.
* Depending on participation, it is expected to generate up
to $2 billion per year in savings, Enbridge ( ENB ) said.
* Project Beacon could also help avoid the use of
higher-emitting fuels, like oil, for power generation.
* The open season runs from May 18 to July 1.
* Project Beacon is separate from Enbridge's ( ENB ) 75-million
cubic feet per day Algonquin Reliable Affordable Resilient
Enhancement (AGT Enhancement), expected to be in service in
2028.
* Based on discussions about the need for more gas in the
region, Enbridge ( ENB ) said Project Beacon could be sized at about 300
mmcfd, depending on customer commitments.