Aug 21 (Reuters) - Entergy's ( ETR ) Louisiana unit
received approval from the Louisiana Public Service Commission
to move forward with infrastructure investments tied to Meta's
new data center in Richland Parish, the utility firm said on
Wednesday.
The approval would allow the unit to construct three new
combined cycle combustion turbine generation facilities, with
two located in Richland Parish, and expected to come online in
2028.
The third facility will be built in Entergy Louisiana's
existing Waterford site in St. Charles Parish, and is expected
to start operations in late 2029.
The company added it will further build several new
transmission facilities for Meta's data center across its
operating areas.