Exclusive-Sanctions delay to Russian zinc mine causes supply miscalculation, sources say
News World Market Environment Technology Personal Finance Politics Retail Business Economy Cryptocurrency Forex Stocks Market Commodities
Exclusive-Sanctions delay to Russian zinc mine causes supply miscalculation, sources say
Nov 3, 2024 11:17 AM

LONDON (Reuters) - Western sanctions on Russia's zinc miner Ozernoye have left it struggling to replace equipment needed to ramp up output, three sources with knowledge of the matter said, meaning mined zinc supply forecasts for 2025 are likely to be too high.

Without Ozernoye's substantial contribution to global mined zinc supply next year, a shortage of zinc concentrate - a raw material to make zinc metal, used to galvanise steel, is likely to persist. Concern over tight supplies is one of the drivers that has pushed zinc prices to a 20-month high.

Asked about the possible delay, Ozernoye told Reuters it plans next year to produce concentrate "in volume comparable to the previously announced targets".

Ozernoye officially launched production in September, saying that it would reach full capacity of about 320,000 metric tons of zinc in concentrate in 2025.

That represents 2.5% of next year's global mined zinc supply estimated at 12.86 million tons, industry group the International Lead & Zinc Study Group (ILZSG) said.

The ILZSG included the ramp-up of Ozernoye in its forecasts of robust growth of 8.9% in new mining zinc supply outside China in 2025.

The sources, who asked not to be named because they were not authorised to speak publicly, said Ozernoye had yet to produce any material as it could not find an adequate replacement for the components that process rocks into powder-form concentrate.

Those parts were damaged by a fire in November 2023.

Ozernoye did not give any production targets when approached by smelters and traders interested in buying their concentrates next year, the sources said.

The components Ozernoye needs were developed and are made by commodity trader Glencore's subsidiary Glencore Technology. Glencore taps an Australian zinc-lead deposit with a similar mineral composition to that of Ozernoye.

Glencore can no longer sell the concentrator parts to Ozernoye, which the U.S. government placed under sanctions shortly after the fire.

Glencore declined to comment. The Swiss trader-miner said only it would "fully comply with all sanctions applicable to our business activities".

Ozernoye is working with local company TEM Partner to try to replicate Glencore's system, one source said. Production may start in November, the same source said.

The company statement said its equipment was made in Russia by its "in-house design bureau".

It said it expected to achieve "project capacity within a year from the start of commissioning," without specifying when that was.

"The part of the flotation equipment, which has already been commissioned, is behaving stably and the first batches of zinc concentrates have been received," it said.

The uncertainty over Ozernoye's output adds to the impact of other disruption, including Century's force majeure and a slower-than-expected ramp-up at Ivanhoe's Kipushi project in Democratic Republic of Congo (DRC).

Reflecting the difficulty of sourcing concentrate, zinc treatment charges (TC), the fees a smelter earns for converting concentrate into refined metal and a gauge of concentrates' availability, dropped to minus $40 a ton end of September, according to pricing agency SMM.

The lower TC pushed some zinc smelters into losses and they had to cut production.

Comments
Welcome to financetom comments! Please keep conversations courteous and on-topic. To fosterproductive and respectful conversations, you may see comments from our Community Managers.
Sign up to post
Sort by
Show More Comments
Related Articles >
SJVN secures 200-MW wind power project at ₹3.24 per unit
SJVN secures 200-MW wind power project at ₹3.24 per unit
Nov 16, 2023
Projected to generate 482 million units in its inaugural year post-commissioning, the cumulative energy generation over a 25-year span is anticipated to reach 12,050 million units. Shares of SJVN Ltd ended at ₹75.17, down by ₹0.50, or 0.66%, on the BSE.
This sustainable jewellery brand is luring some women away from gold
This sustainable jewellery brand is luring some women away from gold
Oct 30, 2023
Aulerth's offerings range from ₹5,000 to as high as ₹2.8 lakh. Are women willing to spend this much on jewellery made from scrap? Founder and CEO Vivek Ramabhadran definitely believes so. Aulerth produces couture-inspired pieces in association with designers like JJ Valaya, Suneet Varma, among others. It has reported 33% repeat customers in the past year and expects a spike to 40% soon.
Suzlon's S144–3 MW wind turbines get big boost from Indian government
Suzlon's S144–3 MW wind turbines get big boost from Indian government
Nov 15, 2023
Th Suzlon wind turbines received the RLMM (Revised List of Models & Manufacturers) listing from the Ministry of New and Renewable Energy, marking an important milestone for the successful commercialisation of the product. Shares of Suzlon Energy Ltd ended at ₹40.49, up by ₹1.85, or 4.79%, on the BSE.
Tata Power Renewable Energy wins 200-MW project in collaboration with SJVN
Tata Power Renewable Energy wins 200-MW project in collaboration with SJVN
Nov 28, 2023
The firm and dispatchable renewable energy (FDRE) project, designed with a hybrid of solar, wind, and battery storage, is aimed at providing a stable and dispatchable energy supply during peak hours. Shares of Tata Power Company Ltd ended at ₹270.75, up by ₹12.60, or 4.88%, on the BSE.
Copyright 2023-2025 - www.financetom.com All Rights Reserved