* MODEC ( MDIKF )-built FPSO to add 250,000 bpd of output capacity
* Exxon to complete recovery of as much as $5 billion in
costs this year
* Whiptail project to begin next year, Hammerhead startup
now forecast for 2028
* Exxon group to seek approval for 9th project, to be
focused on gas
By Kemol King
GEORGETOWN, March 19 (Reuters) - A new floating
production facility for a consortium led by Exxon Mobil ( XOM )
in Guyana is nearly complete and expected to soon depart from
Singapore, an executive said Thursday, part of the push to
accelerate oil and gas projects in a country key to the U.S. oil
giant's growth.
Guyana has allowed Exxon to quickly boost output capacity to
over 900,000 barrels per day (bpd) after only first inaugurating
crude production in 2019. The rapid growth in output has
propelled the small country to the list of top oil producers in
South America.
The floating production, storage and offloading (FPSO) platform
Errea Wittu, being built by Japanese firm MODEC ( MDIKF ), would
be the fifth to be installed by the Exxon group in Guyana. It
will produce, store and deliver up to 250,000 barrels per day
from the Uaru offshore project.
Once that project begins, it could push crude output in
Guyana past its troubled neighbor Venezuela. Exxon expects its
output capacity from all planned projects in Guyana to reach
some 1.7 million bpd by 2030.
It is not clear when the facility will arrive; Exxon had
previously said arrival in Guyanese waters would happen later
this year, without further details. Once it arrives, the vessel
will need testing before it can begin production.
The group's fourth project, Yellowtail, which began last
year, now produces 263,000 bpd, lifting overall output in Guyana
to 916,000 bpd in January. Exxon is expected to seek government
approval to increase Yellowtail's capacity to about 290,000 bpd,
Alistair Routledge, the head of Exxon in Guyana, told reporters
on Thursday.
Benchmark Brent crude prices have shot up to more than $110 a
barrel following attacks on numerous Middle Eastern energy
facilities as the U.S.-Israeli war on Iran continues. But that
high price of oil is now expected to help Exxon recover up to $5
billion in costs in the country this year, rather than in 2027
as originally forecast, Routledge said.
The company and the government are currently in an ongoing cost
dispute over expenses incurred by the oil major; Exxon is
evaluating nominees for an independent expert to resolve the
dispute, Routledge said.
ONE PROJECT AFTER ANOTHER
Following Uaru, Exxon is on track to start the consortium's
sixth project, Whiptail, by the end of 2027, while trying to
accelerate the startup of the seventh project, Hammerhead, for
2028, a year earlier than originally planned, Routledge said.
Plans for subsequent projects are expected to be submitted for
government approval by next year, Routledge added.
Guyana's government has been pressuring the Exxon group to
secure gas output and supply to its shoreline to feed a variety
of industrial projects from power generation to petrochemicals,
but those projects have encountered delays. Exxon has completed
its first $1 billion natural gas pipeline, but it is not yet
operational.
A second, longer natural gas pipeline that would transport
offshore gas to Guyana's Berbice region could cost some $2
billion, Routledge said.