Factbox-US offshore wind farms in service, in construction and under development
News World Market Environment Technology Personal Finance Politics Retail Business Economy Cryptocurrency Forex Stocks Market Commodities
Factbox-US offshore wind farms in service, in construction and under development
Jan 24, 2025 1:09 PM

(Reuters) - U.S. President Donald Trump suspended new federal offshore wind leasing on his first day back in the Oval Office on Jan. 20, pending an environmental and economic review.

On the same day, Danish energy company Orsted, the world's biggest offshore wind firm, posted another impairment charge on delays to a U.S. offshore project.

Those are just the latest blows for the offshore wind industry that former President Joe Biden and several states considered key to meeting federal and state clean energy targets.

"Halting offshore wind represents a huge step backward in our efforts to advance a clean energy future and damages the state's economic opportunities," North Carolina Governor Josh Stein, a Democrat, told Reuters in an email.

"Investors have signed leases and invested significant resources. They deserve certainty," Governor Stein said.

In California, where offshore wind is in early stages of development, Adam Stern, Executive Director of Offshore Wind California, an industry trade group, said most of the work was happening at the state level.

"As an industry, we're focused and moving forward with what is advancing offshore wind in California, and right now most of that is occurring at the state level." That includes approved spending of roughly $475 million to upgrade ports and $4.6 billion to upgrade power transmission lines to prepare for future offshore wind projects.

In 2023 and 2024, several offshore wind companies, including Orsted, took billions in write-offs, impairments and other cancellation fees after they determined they could no longer complete projects profitably due to rocketing construction costs, higher interest rates and supply chain snags.

In New Jersey, which has seen its share of offshore wind project delays, Governor Phil Murphy, a Democrat, told Reuters in an email that he remains committed to clean energy.

"New Jersey will explore all available options to protect the health of our environment and residents while bolstering energy independence, creating good-paying American jobs, lowering energy bills, and growing New Jersey's innovation economy," Governor Murphy said.

There are currently four offshore wind projects operating in the U.S., but one - Vineyard Wind 1 - was shut for part of 2024 after a blade fractured and fell into the ocean in July.

There are also four offshore wind projects under construction and several more in development.

The following factbox lists the projects in service and those under construction and in advanced development that were expected to continue despite Trump's review:

In Service State(s) Company Start First Power Size (MW)

Construction

Project

Block Island RI Orsted 2016 29

Coastal Virginia Offshore Wind Pilot VA Dominion 2020 12

South Fork RI, MA Orsted (50%) and Global Infrastructure Partners (GIP) Skyborn Renewables unit (50%) Feb 2022 Dec 2023 132

Vineyard Wind 1 MA Iberdrola/Copenhagen Infrastructure Partners Nov 2021 Jan 2024 806

Under Construction State(s) Company Start First Power Size (MW)

Construction (Estimated) Estimated

(Estimated)

Revolution Wind RI, MA Orsted (50%) and Global Infrastructure Partners (GIP) Skyborn Renewables unit (50%) 2023 2026 704

Coastal Virginia Offshore Wind (Commercial) VA Dominion (50%)/Stonepeak (50%) Nov 2023 2026 2,587

Empire Wind 1 NY Equinor ( EQNR ) May 2024 ***2027 810

Sunrise Wind RI, MA Orsted Jul 2024 2026 924

Under Development State(s) Company Start First Power Size (MW)

Construction (Estimated) Estimated

(Estimated)

New England Wind 1 MA Iberdrola 2025 2029 791

SouthCoast Wind 1 MA Ocean Winds (EDP/Engie) late 2025 2030 1,287

Community Offshore Wind 1 NY, NJ RWE/National Grid 2027 2030 1,314

MarWin MD US Wind owned by Toto Holding's Renexia 270

Atlantic Shores South 1 NJ EDF/Shell 1,510

Momentum Wind MD US Wind owned by Toto Holding's Renexia 809

Excelsior Wind NY, NJ Copenhagen Infrastructure Partners' Vineyard Offshore 1,314

Leading Light NY, NJ Invenergy/energyRE 2,400

Vineyard Wind 2 MA Copenhagen Infrastructure Partners' Vineyard Offshore 1,200

Community Offshore Wind 2 NY, NJ RWE/National Grid 1,300

New England Wind 2 MA Iberdrola 1,080

*** Empire Wind 1 - 2027 is estimated time of commercial power instead of first power

Comments
Welcome to financetom comments! Please keep conversations courteous and on-topic. To fosterproductive and respectful conversations, you may see comments from our Community Managers.
Sign up to post
Sort by
Show More Comments
Related Articles >
Suzlon's S144–3 MW wind turbines get big boost from Indian government
Suzlon's S144–3 MW wind turbines get big boost from Indian government
Nov 15, 2023
Th Suzlon wind turbines received the RLMM (Revised List of Models & Manufacturers) listing from the Ministry of New and Renewable Energy, marking an important milestone for the successful commercialisation of the product. Shares of Suzlon Energy Ltd ended at ₹40.49, up by ₹1.85, or 4.79%, on the BSE.
This sustainable jewellery brand is luring some women away from gold
This sustainable jewellery brand is luring some women away from gold
Oct 30, 2023
Aulerth's offerings range from ₹5,000 to as high as ₹2.8 lakh. Are women willing to spend this much on jewellery made from scrap? Founder and CEO Vivek Ramabhadran definitely believes so. Aulerth produces couture-inspired pieces in association with designers like JJ Valaya, Suneet Varma, among others. It has reported 33% repeat customers in the past year and expects a spike to 40% soon.
Tata Power Renewable Energy wins 200-MW project in collaboration with SJVN
Tata Power Renewable Energy wins 200-MW project in collaboration with SJVN
Nov 28, 2023
The firm and dispatchable renewable energy (FDRE) project, designed with a hybrid of solar, wind, and battery storage, is aimed at providing a stable and dispatchable energy supply during peak hours. Shares of Tata Power Company Ltd ended at ₹270.75, up by ₹12.60, or 4.88%, on the BSE.
SJVN secures 200-MW wind power project at ₹3.24 per unit
SJVN secures 200-MW wind power project at ₹3.24 per unit