*
Utilities face challenges predicting future power demand
for
data centers
*
Tech companies seek multiple bids, complicating demand
forecasts
*
Rising costs and AI advancements may reduce future power
needs
By Laila Kearney, Seher Dareen
NEW YORK, April 7 (Reuters) - U.S. electric utilities
are fielding massive requests for new power capacity as Big Tech
scours the country for viable locations for new data centers to
keep up with the compute demands of AI.
A Reuters survey of 13 major U.S. electric utility earnings
transcripts found nearly half have received inquiries from data
center companies for volumes of power that would exceed their
peak demand or existing generation capacity - that's everything
they supply to homes and businesses - a metric that reflects the
sheer size of oncoming data center needs.
Now, the power industry is struggling with a question that will
determine the course of billions of dollars in investment: how
to meet the demand?
Utilities have announced billions of additional dollars in
capital spending already this year, with some doubling their
five-year investment plans.
If utilities underestimate the demand, they risk an unstable
electrical grid with a higher chance of blackouts for their
customers. If they overbuild, consumer rate-payers could end up
with the tab.
Complicating matters, tech companies are approaching
multiple power utility providers within the same state, or
across several states seeking multiple bids for the same
project, inflating power demand outlooks, investors and other
power experts said.
"What we're seeing is this huge proposed influx of these
abstract projects that nobody knows anything about," Jon Gordon,
a director at the clean energy trade group, Advanced Energy
United, whose members include clean power and large energy users
like data centers.
The size and secrecy of the inquiries are making it very
difficult for utilities to predict future demand.
"The data center process is to have a competitive bid from
three companies in many markets," said James Richmond, CEO of
e2Companies, an energy management system provider. "That
one-third, automatically, is going to win, and two-thirds is
going to drop out."
BIG DEMANDS
In one example, Sempra ( SRE ) said that its Texas power utility
subsidiary, Oncor Electric, which serves the Dallas area, has
received requests to connect an additional 119 gigawatts, which
is nearly four times the peak electricity use on its system.
Allentown, Pa.-based PPL said it had more than 50 GW
of data center requests, including at least 9 GW in advanced
stages of development, which is higher than its current
generation capacity of 7.2 GW.
Oncor said it only includes data centers in its spending
plan once it has signed agreements with the developer or
operator and has secured collateral in the form of a letter of
credit, an affiliate guarantee or cash.
"We believe these agreements help incentivize accurate
information sharing and the certainty of project planning,"
company spokesperson Kerri Dunn said.
A PPL spokesperson said the company only authorizes spending
on a particular project with an agreement in place.
In utility Evergy's ( EVRG ) territory in Kansas and Missouri, the
pipeline of additional demand driven by data centers has nearly
doubled to more than 11 GW late 2024, which is slightly more
than the maximum demand the utility's entire system is expected
to see at any one point in 2025.
States are beginning to take notice. As a way to gain
insight into the swelling demand forecasts, Pennsylvania is
considering creating a "clearinghouse" for data center power
requests, a representative from the Pennsylvania governor's
office said during a recent industry panel discussion.
"It's something that we're looking at pretty intensely,"
said Jacob Finkel, deputy secretary of policy for Governor Josh
Shapiro.
'RISK OF OVERBUILD'
Big Tech may also decide to abandon projects, which take
years to come to fruition, due to inflation, rising interest
rates, and scarce land.
In 2024, the cost for building a megawatt was nearly $12
million, according to multiple industry sources. But costs to
build out data centers have risen sharply since then, Richmond
said.
Growing capital costs, which may be intensified by tariffs on
materials such as steel imposed by U.S. President Donald Trump,
may also limit the amount utilities will be able to build to
meet demand, said Barclays' analyst Nick Campanella.
"There is risk of overbuild," he said.
In addition to rising costs, there are also signs the needs
of next-generation AI applications may be changing.
New AI models like DeepSeek promise to require less compute, and
therefore potentially far less electricity, by requiring a small
fraction of the chips that are currently being deployed in data
centers.
Fewer chips could mean less power and infrastructure needed
to support them, including the energy-guzzling cooling systems
that are among the main reasons why data centers use so much
energy.
TD Cowen analysts in recent weeks said Microsoft - among the
world's top spenders on AI data centers, with plans to invest
$80 billion this year - had pulled back from projects
representing 2 GW of electricity in the United States and Europe
in the last six months.