June 14 (Reuters) - New Fortress Energy ( NFE ) said on
Friday it expects to start production of liquefied natural gas
at its offshore Altamira-based plant in Mexico in the next ten
days and would begin shipping the gas in July.
The pre-operations and remaining commissioning activities
have been completed, New Fortress said.
The U.S. LNG producer's Altamira plant is Mexico's first
such facility and has been delayed several times.
In May, the company said it expected to export the first
cargo in June. The production deadlines were missed in September
and December last year, as well as in February this year.
Earlier, the company had said the first LNG train, the
liquefaction unit, would cost about $1 billion.