Aug 14 (Reuters) - U.S. liquefied natural gas developer
NextDecade ( NEXT ) said on Wednesday it was exploring all
available legal and regulatory options to ensure the
construction of the first phase of its Rio Grande project in
Texas.
Earlier in August, a U.S. court had overturned the Federal
Energy Regulatory Commission's authorization for the project,
for not issuing a supplemental environmental impact statement.
NextDecade ( NEXT ) said the judicial decision would not come into
effect till the court issued a mandate, which was not expected
to occur until the appeals process had been completed.
"If the ruling stands, the precedent set impacts the
viability of all federally permitted infrastructure projects
because it will be difficult for developers to attract capital
investments until projects receive final unappealable permits,"
CEO Matt Schatzman said.
The company's flagship facility has been in development for
several years and has already suffered repeated delays.
The first phase of the project is expected to reach
completion by early 2029 at an expected cost of about $18
billion.
It is already building the first three liquefaction trains
for the proposed project, which would have the capacity to
produce about 27 million tonnes per annum of LNG, once all of
the trains become functional.
The company, which is backed by the likes of Global
Infrastructure Partners and French energy major Total Energies
, said that overall project completion of the first two
trains stands at 24.1%, as of June.
It has also received purchase orders of about 92% of total
capacity for the first two trains and 88% of the total for the
third train.
The company was planning to start construction of the fourth
liquefaction train in the second half of 2024 after a final
investment decision.