*
All 6 regional grid operators to miss July deadline to
upgrade
equipment
*
Delays could extend 1-2 years past deadline
*
Grid operators cite complexity of project, lack of
software
vendors
By Tim McLaughlin
BOSTON, Jan 31 (Reuters) - U.S. grid operators are
asking regulators for more time to meet a federal order to
upgrade existing transmission lines with equipment that can
boost their capacity up to 40%, according to a Reuters review of
regulatory documents.
The delays represent a potentially years-long setback for
efforts to reinforce the nation's rickety power infrastructure,
at a time newly sworn-in President Donald Trump has declared a
national energy emergency over soaring U.S. electricity demand
from data centers.
The Federal Energy Regulatory Commission in late 2021 had
ordered all six major regional grid operators outside of Texas
to establish systems that regularly update the capacity ratings
on transmission lines, based on weather conditions, by a
deadline of July 2025.
High-voltage transmission lines currently rely mainly on
static settings that do not factor in real-time temperature
drops or cooling breezes that could boost their capacity,
meaning less power is often delivered than could be.
Meeting the FERC order requires technology that factors in
hourly power line temperatures.
All six regional grid operators, however, have indicated
they will not meet the July deadline, according to the Reuters
survey.
Some, including the Midcontinent Independent System Operator
(MISO), which oversees the wholesale electricity market in 15
states, cited a lack of available software vendors needed to
accomplish the work.
MISO told Reuters on Thursday it plans to file a deadline
extension with FERC in March, but has not determined how long of
an extension it would need.
California's CAISO, whose members are now embroiled in
probes and lawsuits relating to devastating wildfires in Los
Angeles, told FERC this week it may need until late 2027 to
fully implement the agency's order.
"Getting this done by the July 2025 time frame is too large
an effort for us and our participating transmission owners,"
Andrew Ulmer, a lawyer for CAISO, said last month during a
meeting with stakeholders, when explaining the rationale for a
deadline extension.
PJM, which operates in 13 states that include the southern
and eastern part of the country, told Reuters it plans to
discuss an extension to the FERC deadline during a meeting with
transmission owners next week.
The Southwest Power Pool, whose territory extends from North
Dakota to Louisiana, told stakeholders earlier this month it
would seek an extension for as late as December 2026.
In early 2024, FERC approved a deadline reprieve for New
York's grid operator that could extend into late 2028.
New England's grid operator, ISO New England, told Reuters
it plans to request a deadline extension in the fourth quarter,
but did not say how long it would need.
The delays are emblematic of decades of underinvestment in
the U.S. electric grid, said Julia Selker, executive director of
WATT Coalition, an advocacy group for more grid technology.
"You need utilities clamoring for this technology to get the
regional grid operators moving," Selker said.
Trump described the electric grid as "increasingly
unreliable" in a Jan. 20 National Energy Emergency declaration,
which is intended to help him fast-track permitting for new
energy infrastructure projects.
FERC told Reuters it is reviewing the president's executive
orders and whether they will factor into decisions on deadline
extensions.
The White House did not respond to a message seeking
comment.
Transmission line congestion cost U.S. electric customers an
estimated $11.5 billion in 2023, according to a report from Grid
Strategies, a power sector consulting firm.
It has been a major obstacle for new power generation
projects, which require transmission capacity to access markets.
Utilities that have already installed sensors based on the
FERC order have seen some benefits.
For example, during 2022's Winter Storm Elliott that knocked
out power for more than 1.5 million homes and businesses across
the U.S., PPL Corp's ( PPL ) power lines with advanced sensors
boosted their capacity beyond standard settings, which PJM said
was critical in avoiding rotating power outages.