HOUSTON, May 13 (Reuters) - Sempra LNG is
revisiting its selection of Bechtel to build its Cameron LNG
expansion project in Louisiana due to rising construction costs,
two people familiar with the matter told Reuters.
The Sempra-Bechtel pricing dispute reflects a broader hike
in construction and labor costs that are affecting several U.S.
liquefied natural gas (LNG) export projects under development
and threaten to further delay others.
Sempra ( SRE ) "has gone back out for an EPC (engineering
procurement and construction) contractor for its expansion
project," one of the people familiar with the matter said.
"High demand for skilled labor for plant construction is
causing costs to rise and making some projects too expensive to
build," the person added.
Sempra LNG operates Cameron, the third largest U.S. LNG
export plant, and is constructing facilities in Mexico and Texas
in addition to pursuing the expansion of the Louisiana plant.
Cameron LNG Phase 2, a venture between affiliates of Sempra
LNG, TotalEnergies, Mitsui ( MITSF ), and Japan LNG
Investment LLC, aims to expand the capacity of the three trains
at its 12 million metric tons per annum (MTPA) facility and add
a fourth.
Sempra LNG CEO Justin Bird had told Wall Street analysts in
March that it was "working with Bechtel on value engineering.
And at this stage, we feel it's best to continue those efforts
while evaluating other potential EPC contractors."
Bechtel Corp's Bechtel Energy had built the first phase of
the Cameron plant, Sempra's ( SRE ) first LNG facility, and is building
the company's newest project, the Port Arthur LNG plant in
Texas.
This month, however, Bird did not mention Bechtel in remarks
on the Cameron expansion, saying only it was working with
unnamed partners to "optimize cost through value engineering."
Sempra ( SRE ) declined to comment on the status of its Cameron
LNG construction contract.
Paul Marsden, the president of Bechtel Energy, also declined
to comment on its status.
"There's no doubt that the whole industry is feeling
inflationary pressures. We need to actively forecast and manage
labor availability and supply chain like never before," he told
Reuters via email.
Last week, the Golden Pass LNG joint venture in Louisiana
acknowledged a dispute with one of its builders. It has delayed
the project startup into 2025.
Sempra ( SRE ) last year said it hoped to give the Cameron expansion
project a financial greenlight in 2024. It subsequently pushed
back the decision until the first half of 2025.