07:57 AM EDT, 03/26/2025 (MT Newswires) -- Talisker Resources ( TSKFF ) said Wednesday that it continues to advance the Bralorne gold project in British Columbia.
The company said it commenced development work as planned at the Mustang mine on March 19, with blasting of a diamond drill bay on the 1120 ramp followed with the initiation of vein access development the 1075 level.
To date, Talisker said 31.6 meters of 3x3-meter development has been completed for vein zone access and auxiliary development.
The company plans to begin parallel development on the 1105 level soon, providing multiple extraction headings on the Alhambra vein. It expects to reach mineralized vein material by the third week in April.
Talisker's share price lost 2.9% on Tuesday to $0.66 on the TSX.