Settlement talks could prevent need for regulatory hearing
*
Dispute stems from budget overruns during Trans Mountain's
expansion
*
Tolling uncertainty has cast doubt on ability of Canadian
government to attract pipeline buyer
By Amanda Stephenson
CALGARY, Oct 22 (Reuters) - The operator of Canada's
Trans Mountain pipeline and oil shippers are in talks to resolve
a shipping cost dispute that has deterred usage of Canada's only
east-west pipeline and hindered the government's plan to sell
it.
Documents filed with the Canada Energy Regulator on Tuesday
by Trans Mountain Corp and a group of oil shippers including
Cenovus Energy ( CVE ), Canadian Natural Resources ( CNQ ),
and ConocoPhillips Canada said the parties are having "active
commercial discussions."
The talks could settle how much the companies pay to ship
oil on the expanded 890,000-barrel-per-day pipeline, which
offers direct access to China and other Asian markets at a time
Canada is trying to diversify oil exports away from the United
States.
A Trans Mountain spokeswoman confirmed in an email on
Wednesday that talks are underway and said the company is
requesting regulatory proceedings be halted to allow time for an
agreement.
Canada's Energy Regulator said it is reviewing the request.
The shippers did not immediately reply to a request for comment.
The more than two-year-old tolling dispute has added uncertainty
to the Canadian government's plans to eventually sell the Trans
Mountain pipeline.
Ottawa, which bought the pipeline for C$4.5 billion ($3.21
billion) in 2018 to rescue the expansion project after years of
regulatory delays and cost increases, began informal talks in
2023 with Indigenous groups along the pipeline's route to
explore their interest in a potential equity stake.
Analysts say it would be difficult for an Indigenous group
or private sector buyer to commit to purchasing the pipeline
until the tolling dispute is settled and Trans Mountain's
long-term revenue potential is clear.
FINAL TOLL UNCERTAINTY
The C$34 billion expansion completed in 2024 tripled the
pipeline's capacity, but the final price tag was nearly
quintuple a 2017 estimate.
While approximately 70% of cost overruns will be borne by
Trans Mountain Corp, the remaining more than $9 billion are to
be covered by tolls under a formula agreed to by shippers and
approved by the Canada Energy Regulator more than a decade ago.
Contracted shippers now pay nearly twice what Trans Mountain
had estimated in 2017. Spot shippers pay even higher rates.
Some shippers have pushed back against the higher tolls,
arguing they are not responsible for cost overruns incurred
during construction. The Canada Energy Regulator had been set to
hold a hearing on the tolls next month.
Since the expansion's startup in May 2024, the Trans Mountain
pipeline has been less full than its operator had earlier
forecast, in part because its higher tolls are deterring
utilization.
If the final toll structure comes in below what Trans
Mountain is looking for, it will make it harder for the pipeline
to recoup its construction costs and could impact its potential
selling price, analysts say.
Trans Mountain CEO Mark Maki said in June he believes the
Canadian government can recover its investment in the pipeline,
but should hold off on the sale until uncertainties around
tolling and utilization are resolved.
($1 = 1.4024 Canadian dollars)