Nov 5, 2024 7:19 AM

09:49 AM EST, 11/05/2024 (MT Newswires) -- (Updates with PJM's statement in the sixth paragraph and recent stock movement in the first paragraph.)

Talen Energy ( TLN ) shares were up over 6% in recent Tuesday trading, a day after the US Federal Energy Regulatory Commission decided to reject an amended interconnection agreement to increase the capacity of an Amazon ( AMZN ) data center connected to Talen's Susquehanna nuclear plant in Pennsylvania, citing concerns over grid reliability and consumer costs.

"Co-location arrangements of the type presented here present an array of complicated, nuanced and multifaceted issues, which collectively could have huge ramifications for both grid reliability and consumer costs," FERC Commissioner Mark Christie said in a Friday filing.

PJM Interconnection, a regional transmission organization, submitted an amended interconnection service agreement between PJM, Talen's Susquehanna Nuclear and PPL Electric Utilities seeking to increase the data center's power capacity from 300 megawatts to 480 MW, according to the filing.

"Talen believes FERC erred and we are evaluating our options, with a focus on commercial solutions," Talen Energy ( TLN ) said in a statement on Sunday.

The company said it can continue to develop the first phases of the Amazon Web Services data center with the previously approved 300 megawatts.

"PJM is reviewing the Commission's order and assessing its implications," PJM said in response to MT Newswires' request for comment. "PJM will continue to work with the Commission, parties to agreements, stakeholders, and the states on issues relating to the co-location of large loads."

Amazon ( AMZN ) and PPL Electric Utilities did not immediately respond to requests for comment from MT Newswires.

Price: 180.44, Change: +10.44, Percent Change: +6.14

Comments
Welcome to financetom comments! Please keep conversations courteous and on-topic. To fosterproductive and respectful conversations, you may see comments from our Community Managers.
Sign up to post
Sort by
Show More Comments
Related Articles >
Kolibri Global Energy Reduces 2024 Guidance as New Production Delayed
Kolibri Global Energy Reduces 2024 Guidance as New Production Delayed
Jul 8, 2024
07:39 AM EDT, 07/08/2024 (MT Newswires) -- Kolibri Global Energy ( KGEI ) reported Monday slight reductions to its 2024 guidance as new production will be added later than originally forecast. Kolibri said its newest wells will take longer to drill and complete, and most of the benefits of these wells will be realized in 2025. We believe the anticipated...
Soma Gold's Cordero Mine and El Bagre Gold Complex Blockaded by Local Community; Company Reports Q2 Production
Soma Gold's Cordero Mine and El Bagre Gold Complex Blockaded by Local Community; Company Reports Q2 Production
Jul 8, 2024
07:41 AM EDT, 07/08/2024 (MT Newswires) -- Soma Gold ( SMAGF ) , which jumped about 10% last Friday, on Monday reported a temporary suspension of mining and processing activities at its el Bagre mine and mill in Antioquia, Colombia, due to a local community blockade. The site has been put on Care and Maintenance status. According to Soma Gold...
Vista Outdoor Board Endorses CSG's Amended Offer, Rejects MNC's Bid As Insufficient
Vista Outdoor Board Endorses CSG's Amended Offer, Rejects MNC's Bid As Insufficient
Jul 8, 2024
Vista Outdoor Inc. ( VSTO ) disclosed an amendment to its merger agreement with Czechoslovak Group a.s., which increases the purchase price payable by CSG for the acquisition of The Kinetic Group business by $100 million to $2.1 billion.  The amendment also raises the cash consideration for Vista Outdoor ( VSTO ) stockholders to $21.00 per share of Vista Outdoor ( VSTO ) common...
--Tesla Shareholders to Urge Judge to Deny $7 Billion Legal Fee in Musk Pay Case, Reuters Reports
--Tesla Shareholders to Urge Judge to Deny $7 Billion Legal Fee in Musk Pay Case, Reuters Reports
Jul 8, 2024
07:39 AM EDT, 07/08/2024 (MT Newswires) -- Price: 248.73, Change: -2.79, Percent Change: -1.11 ...
Copyright 2023-2026 - www.financetom.com All Rights Reserved