May 22 (Reuters) - U.S. natural gas pipeline venture
Mountain Valley Pipeline pushed back the target in-service date
of its long-delayed pipe from West Virginia to Virginia to early
June from the prior target of "prior to June 1".
The company told federal energy regulators in a filing late
Tuesday that the small delay was "due to the extended
construction duration to achieve weld-out, which has been
associated with weather and environmental protection."
The $7.85 billion Mountain Valley project is the only big
gas pipeline under construction in the U.S. Northeast. It has
encountered numerous regulatory and court fights that have
stopped work several times since construction began in 2018.
The pipe, which is key to unlocking gas supplies from
Appalachia, the nation's biggest shale gas-producing region,
needed a bill from the U.S. Congress that was signed into law by
President Joe Biden and help from the Supreme Court before it
could restart construction.
On April 22, Mountain Valley sought authorization from the
U.S. Federal Energy Regulatory Commission (FERC) to put the
project in service by May 23 to meet the "prior to June 1" in
service target.
Since then, Mountain Valley said in the FERC filing that the
project is nearly "welded out," with fewer than ten welds
remaining to allow testing for mechanical completion out of more
than 51,000 welds project-wide.
Hydro testing has been successfully completed on
approximately 99% of the project facilities, with the final
hydrotest to be completed shortly after weld-out, the company
said.
Earlier in May, the company said it repaired a segment of
pipe that failed a water test.
Commissioning is complete for all project compressor
stations and facilities are packed with gas between the northern
terminus of the project and milepost 186.1, the company also
said.
When Mountain Valley started construction in February 2018,
U.S. energy company Equitrans Midstream ( ETRN ) with a roughly
49% interest, the lead partner building the project, estimated
the 2.0-billion cubic feet per day project would cost about $3.5
billion and enter service by late 2018.
The 303-mile (488-kilometre) Mountain Valley project is
owned by units of Equitrans, NextEra Energy,
Consolidated Edison ( ED ), AltaGas ( ATGFF ) and RGC Resources ( RGCO )
. Equitrans will operate the pipeline.