RAF FAIRFORD, England, July 20 (Reuters) - The United
States has resumed taking delivery of F-35 jets with an interim
upgrade after a months-long halt due to software delays, and
will withhold some payments until remaining enhancements are
ready, senior officials said on Saturday.
Lockheed Martin ( LMT ) and key suppliers have been
upgrading the jets under a programme called Technology Refresh 3
- or TR-3 - that aims to improve displays and processing power.
"We are starting to accept deliveries of TR-3...It is a
truncated version...and does not have all the functionality that
we want, but it is far enough along that we can accept delivery
now," Secretary of the Air Force Frank Kendall said.
TR-3 involves both hardware and software improvements and is
seen as a pillar of a wider upgrade to the stealth jet known as
Block 4.
"The hardware of that seems to be coming along fine but the
software is lagging," Kendall told reporters at the Royal
International Air Tattoo in Britain.
"We are at a point now where we can accept aircraft with the
understanding that additional increments of software have to go
in to get it to where we need it to be."
Andrew Hunter, assistant Air Force secretary for
acquisition, technology and logistics, said the decision to
restart deliveries without the full software upgrade had been
taken in part to prevent knock-on delays to other features.
"Waiting and waiting and waiting to finalise those
capabilities that weren't quite ready is actually holding up
progress on some of the later capabilities that we also really
need," he said.
Hunter confirmed the Pentagon will continue to withhold some
final payments for each jet, but did not specify the amount.
About $7 million of the final payment for each jet, worth
roughly $100 million each, has been withheld to date.
"Not everything we contracted for has been delivered... We
will not pay for that which we have not received," Hunter said.
He added, however, that the scramble to complete TR-3 had
helped improve co-operation between companies on the world's
largest defence programme.
"We are going to work very hard to ensure that that process
of bringing down those barriers continues so that Block 4 comes
through when we need it," he said.