*
Enbridge ( ENB ) wants case heard in federal, not state, court
*
Michigan aims to stop Straits of Mackinac pipeline's use
By Nate Raymond
June 30 (Reuters) - The U.S. Supreme Court agreed on
Monday to hear Enbridge's ( ENB ) bid to change the venue of
Michigan's lawsuit seeking to force the Canadian pipeline
operator to stop operating a pipeline underneath the Straits of
Mackinac, waterways linking two of the Great Lakes, over
environmental concerns.
The justices took up Enbridge's ( ENB ) appeal of a lower court's ruling
rejecting the company's request to move the case from state
court into federal court, a venue generally considered more
friendly to defendants in such cases.
The Supreme Court is due to hear the case in its next term,
which starts in October.
Calgary-based Enbridge ( ENB ) has been locked in a long-running
dispute with Michigan over the aging Line 5 pipeline, which
ships 540,000 barrels per day of crude and refined products from
Superior, Wisconsin, to Sarnia, Ontario.
A four-mile (6.4-km) section of the aging pipeline runs
underwater through the Straits of Mackinac, which connect Lake
Michigan and Lake Huron, and environmentalists are concerned
about the risk of an oil leak.
The Cincinnati-based 6th U.S. Circuit Court of Appeals last
year ruled that Enbridge ( ENB ) waited too long to seek to have the
lawsuit that was brought by Democratic Attorney General Dana
Nessel in June 2019 removed to federal court when it tried to do
so in November 2021. The lawsuit sought to enjoin Enbridge's ( ENB )
continued operation of Line 5 based on alleged violations of
state public nuisance and environmental laws.
Nessel's office in court papers described the 6th Circuit's
ruling as the correct result in a case in which Enbridge ( ENB ) missed
by more than two years the statutory deadline to try to transfer
the litigation to federal court.
Enbridge's ( ENB ) lawyers in a petition to the Supreme Court said
that the 6th Circuit's ruling added to a split within the
regional U.S. appeals courts over whether the judiciary can
create exceptions for a 30-day time limit to seek to remove
cases filed in state court to federal court.
That split has created untenable uncertainty in the law that
resulted in defendants in some parts of the country being
subject to the strict deadline while others were not, Enbridge ( ENB )
told the Supreme Court.
The U.S. Army Corps of Engineers last month said it expects to
make a decision this fall on whether to grant a permit to
Enbridge's ( ENB ) proposal to build a tunnel to house the Line 5
pipeline. In April, Enbridge's ( ENB ) Line 5 project received emergency
designation after President Donald Trump declared a national
energy emergency in a January executive order, giving the Army
Corps the ability to fast-track its review of the project.
Nessel filed the lawsuit in state court in Ingham County.
While that case was being actively litigated before a state
court judge, Michigan Governor Gretchen Whitmer, a Democrat, in
November 2022 revoked an easement that allowed the pipeline to
be operated and filed a lawsuit to enforce the revocation.
Enbridge ( ENB ) succeeded in getting that case transferred from
state court to federal court, having argued that Whitmer's
state-law claims raised federal questions related to foreign
affairs and were potentially preempted by the federal Pipeline
Safety Act and the Submerged Lands Act.
A federal judge rejected Whitmer's bid to remand the case to
state court in November 2021. Based partly on that order,
Enbridge ( ENB ) a month later moved to have Nessel's earlier lawsuit
also transferred to federal court.
Enbridge ( ENB ) argued it could transfer the case 887 days after
receiving Nessel's lawsuit based on a provision of the statute
governing case removals that allows a case to be removed 30 days
after an order from which it could be first determined a case
could be heard in federal court.