HOUSTON, Jan 29 (Reuters) - Venture Global LNG
could finish power generator repairs by the end of February, a
federal inspection report said on Wednesday, potentially
clearing the way for the almost three-year commissioning of the
Calcasieu Pass LNG plant to reach completion.
Venture Global ( VG ) is the most valuable U.S. LNG company
following its initial public offering on Thursday. It has blamed
its inability to deliver cargoes from Calcasieu Pass to its
long-term customers on equipment failures and the unreliability
of its power generators.
The delays led to contract arbitration cases brought by some
of the world's top oil and gas producers, including BP,
Shell, Edison, Orlen ( PSKOF ) and Repsol
.
A "fifth and final" generator project was under way "and
completion is expected by February 2025," inspectors from the
Federal Energy Regulatory Commission said on Wednesday in a
regulatory filing.
The inspection was conducted one week ago and found Venture
Global ( VG ) had made so much progress that a temporary fix suggested
by FERC was no longer necessary, the inspection report said.
Venture Global ( VG ) was not immediately available for comment.
Shell said it was waiting for its cargoes to be delivered.
"For almost two years we've been told by Venture Global ( VG ) that
deliveries were forthcoming. It's never happened. They have
proven to be an unreliable supplier and, until we receive our
contracted cargoes, we will continue to view them that way," a
Shell spokesperson told Reuters.
A Repsol spokesperson said it had no further information on
timing.
Venture Global ( VG ) has said it expects to move from
commissioning to commercial operations at Clacasieu Pass by the
end of the first quarter of 2025.