HOUSTON/WASHINGTON, Dec 4 (Reuters) - Venture Global LNG
on Wednesday slammed a U.S. call for an additional environmental
review of a proposed Louisiana LNG project as unnecessary,
adding that it will be ready to begin construction once the
project gets a final go-ahead.
The Federal Regulatory Energy Commission (FERC) last week
pulled Venture Global LNG's authorization to construct its CP2
export facility, requiring an additional environmental review of
air quality impact.
The additional review follows a decision on Aug 6 from the
U.S. Court of Appeals for the District of Columbia Circuit that
quashed FERC's approval of NextDecade's ( NEXT ) plant at the Port of
Brownsville, Texas, and ordered FERC to reconsider the project
ramifications with a new environmental statement and public
comment period.
CP2 has been at the center of a fight with environmentalists
seeking to limit future LNG projects on the U.S. Gulf Coast. The
20 million ton per annum facility won FERC construction approval
in June.
Venture Global did not say if the decision would delay
construction nor if it had already begun site work.
Engineering and construction giant Worley won a
contract last year to build the first phase of CP2. It did not
immediately respond to a request for comment.
"CP2 LNG unquestionably meets or exceeds all required
environmental air standards as determined by FERC in its July
2024 order and will be formally replying to the commission in
the coming days," a Venture Global spokesperson said.
FERC also put on hold its approval for the construction of
Commonwealth LNG's planned 9.5 Mtpa LNG export facility in
Cameron, Louisiana. Commonwealth said it remained confident in
its project and will be providing all requested input for the
supplemental environmental impact statement.