07:13 AM EDT, 08/18/2025 (MT Newswires) -- Westshore Terminals Investment ( WTSHF ) overnight Sunday reported a fire on the shiploader that services Berth 1 and lowered its 2025 throughput guidance.
The fire was extinguished and there were no injuries, but the outage is expected to cut throughput volumes to between 24 million tonnes to 24.5 million tonnes, from 26 million tonnes. Preliminary inspections suggest that Berth 1 will be out of commission for about 10 weeks, a statement said.
Westshore will provide a more accurate estimate once a detailed inspection has been performed. Berth 2 operations will continue throughout the repair work.
Westshore Terminals, located in Delta, British Columbia, is Canada's busiest coal export terminal.