The Rafale deal negotiated by the National Democratic Alliance (NDA) government to procure 36 fighter jets was 2.86 percent cheaper than the United Progressive Alliance's (UPA) 2007 offer, the Comptroller and Auditor General (CAG) said in its report.

Share Market Live

NSE

The report gives much relief to the Narendra Modi government, which has been facing fervent attacks by the Congress and other opposition parties over the fighter jet deal.

The centre has repeatedly denied allegations by the opposition parties in the Rafale issue inside and outside the Parliament.

Follow our Parliament live blog on CAG's report for more updates.

Key highlights from the CAG report on the Rafale Jet deal

On Delivery Schedule: The CAG report said there was an improvement of one month in the delivery schedule of the 2016 contract versus 2007. The Indian Negotiating Team (INT) had apprehensions about the achievements of even this delivery schedule.

The contracted schedule for 36 Rafale jets was 71 months late as compared to the 72 months delay in 2007 during the UPA rule.

On Cost Of Procurement: The report added the basic flyaway aircraft was bought at the same price as the 2007 UPA aircraft.

Background: The offer of 2007 had two distinct packages – 18 flyaway aircraft package and pricing for transfer of technology (ToT) package of 108 aircraft to be produced in India. The offers made in 2015 was only for 36 flyaway fighter aircrafts. For comparing the prices of 2007 and 2015, the scope of both offers had to be brought at par.

Findings: Overall the 2015 deal price was 2.86 percent cheaper than the 2007 price, the CAG report said, adding that the offer made on the missile procurement implied a cost saving of 17.08 percent.

The vendor charged an excess of 6.54 percent more in the area of engineering support package (ESP) and in the area of performance based logistics.

The vendor also charged 2.68 percent more in the area of training and 1.05 percent less in the area of weapon package.

On India Specific Enhancements: During the negotiations of 2015 for 36 aircraft, the defence ministry rejected INT’s proposal to reduce the number of India specific enhancements by six. Four of the India specific enhancements (14 percent of the total cost of enhancements) were found to be unnecessary by technical and staff evaluations, the report added.

On Bank Guarantee: The offer made in 2007 had included 15 percent bank guarantee against advance payments. In the 2015 offer, there were no financial and performance bank guarantees.

The French government and vendor provided a Letter of Comfort signed by the French Prime Minister despite the law ministry advising that a government or a sovereign guarantee be procured, the report added.

The savings made on the ‘No Bank Guarantee’ went to the vendor and not to the Indian government, the report added. The total savings accruing to the vendor by not having to provide guarantee was to be passed on to the government.

The audit found that this was actually saving for the vendor when compared with its previous 2007 offer.

On Price Comparison: "Comparison of prices under 2007 and 2015 offers has posed its own difficulties because the package it offered in 2007 included the price of license production of 108 aircraft in India while the 2015 offer included only direct flyaway aircraft, which was compared costs of 18 flyaway aircraft. Costs are fungible," the report said.

The report further said, "The difference between the aligned price estimated by INT and audit could be attributed to inconsistent price variation factors adopted by INT, alignment of the quantities or scope of the two offers and the difficulties of alignment itself as stated earlier."

With regard to India specific enhancements, the deal was 17.08 percent cheaper, said the CAG report, which was tabled in Parliament on Wednesday.

In terms of engineering support package and performance-based logistics, the deal was 6.54 percent expensive, it stated.

The NDA deal was 2.86 percent cheaper than the one negotiated by the UPA government in 2007, according to the report.

(With inputs from agencies)

First Published:Feb 13, 2019 1:24 PM IST

Comments
Welcome to financetom comments! Please keep conversations courteous and on-topic. To fosterproductive and respectful conversations, you may see comments from our Community Managers.
Sign up to post
Sort by
Show More Comments
Related Articles >
Dallas Fed President Logan Says 'Gradual' Rate Reduction Could Help Manage Risks
Dallas Fed President Logan Says 'Gradual' Rate Reduction Could Help Manage Risks
Oct 9, 2024
09:36 AM EDT, 10/09/2024 (MT Newswires) -- The Federal Open Market Committee should proceed cautiously as it lowers interest rates so that it can be prepared for any surprises, Dallas Federal Reserve Bank President Lorie Logan said Wednesday at the Future of Global Energy Conference. If the economy evolves as I currently expect, a strategy of gradually lowering the policy...
Fed's Musalem argues for more rate cuts, says data to drive easings
Fed's Musalem argues for more rate cuts, says data to drive easings
Oct 7, 2024
NEW YORK (Reuters) - Federal Reserve Bank of St. Louis President Alberto Musalem said on Monday he supports more interest rate cuts as the economy moves forward on a healthy path, while noting that it is appropriate for the central bank to be cautious and not overdo easing monetary policy. Further gradual reductions in the policy rate will likely be...
US Dollar Rises Early Wednesday Ahead of Wholesale Inventories, FOMC Minutes, Fed Appearances
US Dollar Rises Early Wednesday Ahead of Wholesale Inventories, FOMC Minutes, Fed Appearances
Oct 9, 2024
07:48 AM EDT, 10/09/2024 (MT Newswires) -- The US dollar rose against its major trading partners early Wednesday ahead of a lighter data schedule but a heavy slate of nine appearances by Federal Reserve officials. Earlier Wednesday, the Mortgage Bankers Association said the strong September employment data released last week lifted mortgage rates to their highest level since August in...
US wholesale inventories revised lower in August
US wholesale inventories revised lower in August
Oct 9, 2024
WASHINGTON (Reuters) - U.S. wholesale inventories rose less than initially thought in August amid a sharp moderation in the pace of increase in motor vehicle stocks, a trend that if sustained could temper expectations for robust economic growth in the third quarter. The Commerce Department's Census Bureau said on Wednesday that wholesale inventories edged up 0.1%, revised down from the...
Copyright 2023-2026 - www.financetom.com All Rights Reserved