PARIS, Feb 17 (Reuters) - Airbus is struggling
to increase output of its A350 jetliner as it faces ongoing
delays in the arrival of fuselage parts from Spirit AeroSystems ( SPR )
, industry sources said.
The delays have cast doubt on Airbus' ability to increase
production above current rates of around six jets a month for at
least the rest of this year, though it still hopes to reach its
published target of 12 a month during 2028, they added.
A spokesperson for Airbus declined comment but referred back
to comments given with its nine-month results in October, when
Airbus upheld the 2028 target but said it was "actively managing
specific supply chain challenges" that may affect 2025 output.
Spirit AeroSystems ( SPR ) declined comment.