07:47 AM EDT, 08/26/2024 (MT Newswires) -- NG Energy International ( GASXF ) on Monday announced the commissioning of the 28.3 km pipeline in Colombia from Jobo to the Brujo Central Processing Facility (CPF) at Sinu-9 by its partners INFRAES and Kronos.
NG expects to start gas sales by the first week of September, with a gradual and steady ramp-up to full production by the end of September.
The company has also appointed Leonardo Chavez as vice president of operations to help oversee Phase-2 at Sinu-9 and evaluate production optimization and growth opportunities at Maria Conchita production facilities. He has over 23 years of experience in the oil and natural gas industry, including as chief operating officer for Bond Energy Solutions in Colombia