*
Constellation fast-tracks Three Mile Island restart for
Microsoft ( MSFT ) data centers
*
PJM expedites grid connection for select projects
*
Nuclear power interest resurges amid U.S. electricity
demand
growth
(Adds comments from press event at Three Mile Island in
Pennsylvania)
By Laila Kearney
THREE MILE ISLAND, Pennsylvania, June 25 (Reuters) - The
former Three Mile Island nuclear power plant in Pennsylvania may
restart in 2027, about a year ahead of schedule after being put
on a fast track to connect to the regional grid, executives with
the plant's owner Constellation Energy ( CEG ) said on
Wednesday.
Constellation struck a deal last September to power Microsoft ( MSFT )
data centers, paving the way to reopen Three Mile
Island, widely known as the site of a partial meltdown in 1979
that chilled the nuclear industry.
Constellation's 20-year power purchase agreement with
Microsoft ( MSFT ) is emblematic of the dramatic lengths Big Tech has
been willing to go to fuel its artificial intelligence
expansion, which began to intensify a year-and-a-half ago.
The reactor re-entering service at Three Mile Island, which
is being renamed the Crane Clean Energy Center, was not part of
the 1979 accident, and shut in 2019 for economic reasons.
"We made a mistake in shutting down this plant, but we're not
here to dwell on the past," said Constellation CEO Joe Dominguez
at an event on Three Mile Island, backed by giant cooling towers
and the nuclear plant that will be brought back as Crane.
The nuclear building is in similar shape to when it shut in
2019, and since the restart announcement, most of the work has
been around planning and hiring, Constellation said.
The company has ordered several key items for the restart,
including its main transformer and fuel. It has also restored
water systems needed to run the plant and completed various
infrastructure inspections needed for permitting approvals.
At the time of the restart announcement last year,
Constellation said it expected the plant to re-open in 2028.
Officials with the company had said they expected the process to
be slowed by wait times associated with connecting power
projects to the regional grid, which is operated by PJM
Interconnection.
"When PJM gets this connected, we're going to be ready,"
Dominguez said on Wednesday.
Despite the enthusiasm, nuclear power plant projects have
historically been far over budget and behind schedule.
No fully shut nuclear power plant has been restarted,
but at least one other attempted restart - of the Palisades
nuclear plant in Michigan - is under way.
As the technology industry drives U.S. electricity
demand to record highs, nuclear power has broadly seen a
resurgence of interest after decades in decline.
New York
plans to build a new nuclear power plant, which would be one
of the first to be constructed in a generation.
FAST-TRACKED PROJECTS
Hundreds of Constellation workers joined Wednesday's event,
along with PJM CEO Manu Asthana and Pennsylvania Governor Josh
Shapiro, who pushed for the restart to be fast-tracked for
approval through PJM.
Power projects can linger in PJM's queue, which is
essentially the application and engineering study process to
hook up a power plant to the broader grid. PJM's territory spans
13 states and the District of Columbia, covering about 67
million customers.
As a way to alleviate some of that bottleneck, particularly
as data centers rapidly proliferate on PJM's territory, the
country's largest grid operator has fast-tracked its
interconnection process for select projects.
Crane was the largest of the projects expedited by PJM, Shapiro
said.
"I am focused like a laser beam on the future of Pennsylvania
and the future runs through places right here like Crane," he
said.
More than 400 people have been hired to work at the
plant so far, and there are 30 operators who can work in control
rooms in training for the reopened plant, according to Dominguez
and other Constellation officials.
The Nuclear Regulatory Commission is expected to visit
Crane in July to observe the training process, they said.